Popchev stone design LTD

6 project

Recovering SMEs by improving energy efficiency

Total cost

273,000.00

Grant

136,500.00

Self finance

136,500.00

Total paid

0.00

Status

In execution (starting date)

Contract date

16 Sep, 2022

Start date

16 Sep, 2022

End date

16 Jul, 2023

Supporting medium-sized enterprises to overcome the economic impact of the COVID-19 pandemic

Total cost

150,000.00

Grant

150,000.00

Self finance

0.00

Total paid

0.00

Status

Closed (completion date)

Contract date

08 Feb, 2021

Start date

08 Feb, 2021

End date

08 May, 2021

Modernizing the production process, increasing the production capacity and increasing the export potential of Popchev Stone Design Ltd, by purchasing new equipment in Slanchevo

Total cost

243,000.00

Grant

218,700.00

Self finance

24,300.00

Total paid

218,655.00

Status

Closed (completion date)

Contract date

12 Feb, 2019

Start date

12 Feb, 2019

End date

10 Feb, 2020

Increasing the potential of the employed Popchev stone design EOOD by increasing the qualification of the workers in the field of stonework

Total cost

39,600.00

Grant

39,600.00

Self finance

0.00

Total paid

0.00

Status

Terminated (termination date)

Contract date

21 Feb, 2018

Start date

01 Apr, 2018

End date

30 Jun, 2019

Increasing the energy efficiency in "Popchev stone design" LTD

Total cost

1,917,460.57

Grant

1,163,973.35

Self finance

753,487.22

Total paid

1,137,385.85

Status

Closed (completion date)

Contract date

17 Aug, 2017

Start date

17 Aug, 2017

End date

26 Feb, 2019

Developing the management capacity of "Popchev stone design" LTD by implementing an ERP system

Total cost

126,100.00

Grant

88,270.00

Self finance

37,830.00

Total paid

87,683.40

Status

Closed (completion date)

Contract date

06 Mar, 2017

Start date

06 Mar, 2017

End date

13 Aug, 2018