With the financial support from the Rural Development Program 2014-2020, SOUTH FRUIT Ltd. intends to establish a processing plant for agricultural production in 005002 plot in the area of Svetoslav village, Stambolovo municipality, Haskovo. For realization of its intention the company will make the following investments: Construction and assembly activities, Vertical planning, Reservoir for technological needs, Tank for fire-fighting needs, Gas supply, Heating, ventilation and air-conditioning installations, Refrigeration installations, Purchase and installation of technological equipment.
Overview
| Status | Contracted |
|---|---|
| Start date | 04 Dec, 2019 |
| End date | 04 Dec, 2022 |
| Contract date | 04 Dec, 2019 |
Programme
Beneficiary
Financial information
| Total cost | 2,625,716.10 |
|---|---|
| Grant | 1,312,858.04 |
| Self finance | 1,312,858.06 |
| Total paid | 0.00 |
| EU participation percent | 75.0% |
Location