Modernization of dairy processing plant / dairy /

modernization of an existing dairy for the processing of organic certified milk into the main product - "Halumi" grill, and by-products, butter and curd obtained as a result of reverse osmosis of the whey after the main production

Comments
Leave a comment

Overview

Status Contracted
Start date 10 Dec, 2019
End date 10 Dec, 2022
Contract date 10 Dec, 2019
View in UMIS

Financial information

Total cost 3,059,362.94
Grant 1,529,681.44
Self finance 1,529,681.50
Total paid 0.00
EU participation percent 75.0%

Location