The investment intention of LILI 1204 ltd. is the reconstruction of an existing building in a workshop for the production of wooden shuttering, located in the land estate №045131, Kramy Dol in the village of Saparevo, Municipality of Sapareva Banya. In the factory for the production of wooden shuttering panels of solid wood will be produced glued canvas sizes up to 600 / 2000mm and thickness up to 3cm. The annual production capacity of the plant is 674m3. The building is existing and construction works are required. The building after the reconstruction will consist of a production hall, warehouse and sanitary-household premises.
Overview
Status | Contracted |
---|---|
Start date | 06 Oct, 2020 |
End date | 15 Sep, 2023 |
Contract date | 06 Oct, 2020 |
Programme
Beneficiary
Financial information
Total cost | 495,828.74 |
---|---|
Grant | 247,914.37 |
Self finance | 247,914.37 |
Total paid | 0.00 |
EU participation percent | 85.0% |
Location