The present project includes the reconstruction of streets in the city of Kresna: "Yane Sandanski", from a.p.131 to a.p.1, "Vlachinski ezera", from a.p.157 to a.p.149. "Pirin" from a.p.130 to a.p.136, "Spartac" from a.p.153 to a.p.151, and "Tsar Samuil" from a.p.131 to a.p.135, Reconstruction of Existing Pavements in the city of Kresna: "Yane Sandanski" from a.p.131 to a.p.1, "Spartac" from a.p.153 to a.p.151, "Tsar Samuil" from a.p.131 to a.p.135
Overview
| Status | Contracted |
|---|---|
| Start date | 07 May, 2019 |
| End date | 07 May, 2022 |
| Contract date | 07 May, 2019 |
Programme
Beneficiary
Financial information
| Total cost | 1,165,968.11 |
|---|---|
| Grant | 1,165,968.11 |
| Self finance | 0.00 |
| Total paid | 582,984.03 |
| EU participation percent | 85.0% |
Location