The project envisages reconstruction and repair on the street in two settlements from the municipality of Oryahovo: gr.Orjahovo and s.Selanovtsi. In town Oryahovo street: "Arch.Dimiter Colov", str: "9-ti novemvri", str: "Vitosha", str: "Denkouglu", in village Selanovtsi str: "Stefan Stambolov". The necessity of the realization of the project was borne, since the municipal street network as a result of insufficient and irregular financing of the repair and support was offended and demolished. Contaminated sites with impaired drainage, disturbed road, decay and other defects requiring a full reconstruction and rehabilitation of the street network. A complete overhaul will be performed. There will be horizontal marking and vertical signalization.
Overview
Status | Contracted |
---|---|
Start date | 08 May, 2019 |
End date | 08 May, 2022 |
Contract date | 08 May, 2019 |
Programme
Beneficiary
Financial information
Total cost | 1,135,940.66 |
---|---|
Grant | 1,135,940.66 |
Self finance | 0.00 |
Total paid | 547,857.96 |
EU participation percent | 85.0% |
Location