Reconstruction and rehabilitation of existing streets in the town of Apriltsi under sub-measure 7.2 "Investments in the creation, improvement or extension of all types of small scale infrastructure" from measure 7 "Basic services and renovation of rural villages" of the Rural Development Programme 2014-2020

The street network on the territory of the town of Apriltsi is in poor exploatation condition, as well as fractured, fallen and compromised edges of the pavement, which is a prerequisite for difficult access to the republic road network, connecting with the municipal center. The street network on the territory of Apriltsi municipality plays a major role in the lives of locals as it provides the main transport links within the municipality. It is therefore of utmost importance that the street network on the territory of Apriltsi Municipality is in good condition in order to ensure unimpeded and safe connection with the nearby and outermost settlements. This project proposal provides for the reconstruction and rehabilitation of the following streets in town of Apriltsi: - Otdih Street, Ostrets district from OK 177 to OK 111 in the town of Apriltsi; - Chuklata Street, Novo Selo district, in the town of Apriltsi; - Vulko Yonkov Street, Novo Selo district in the town of Apriltsi; - Novo Selo Street, Novo Selo district in the town of Apriltsi; - Targovska Street, Novo Selo district in the town of Apriltsi; - Pastuhanska Street, Zla Reka district in the town of Apriltsi; - Radevska Street, Zla Reka district in the town of Apriltsi; - Hrizantema Street, Novo Selo district in the town of Apriltsi. The project also provides for accompanying activities such as: author supervision, construction supervision and project management. The main objective of the present project is the achievement of a balanced territorial development through the complex improvement of the state of the technical infrastructure on the territory of the Municipality of Apriltsi. The aim of Apriltsi municipality is through the implementation of the project to achieve an active einvorment and development of social and economic attractiveness.

Comments
Leave a comment

Overview

Status Contracted
Start date 23 May, 2019
End date 23 May, 2022
Contract date 23 May, 2019
View in UMIS

Financial information

Total cost 1,161,504.66
Grant 1,161,504.66
Self finance 0.00
Total paid 0.00
EU participation percent 85.0%

Location