With a project proposal "Reconstruction of" Georgi Kyoseivanov " street and "Ivan Vazov" street from p. 313 to p. 338 and Izgrev street from p. 148 to p. 312 " is envisaged to improve the transport and operating qualities of the road surface of the following streets located in the territory of Peshtera Municipality by reconstruction of total 1206,42 m: - Georgi Kyoseivanov street from km 0 + 455,78 to km 0 + 873, town of Peshtera - length 417,22 m - Ivan Vazov street from p. 313 to p. 338 and Izgrev street from p. 148 to p. 312", the town of Peshtera - length 789,20 m Reconstruction of the street network will also improve the transport infrastructure in the town of Peshtera and will ensure the normal movement of local and foreign citizens, tourists and others. This will significantly improve the quality of life not only for the inhabitants of these streets but also for the population of the whole villages and even the entire municipality as the settlement is the municipal center of Peshtera Municipality.
Overview
Status | Contracted |
---|---|
Start date | 21 May, 2019 |
End date | 21 May, 2022 |
Contract date | 21 May, 2019 |
Programme
Beneficiary
Financial information
Total cost | 1,006,455.57 |
---|---|
Grant | 1,006,455.57 |
Self finance | 0.00 |
Total paid | 500,952.03 |
EU participation percent | 85.0% |
Location