Project "Supply and installation of artificial flooring and facilities for basketball and volleyball playground", in Regulated School I-school, kv.101 according to the plan of the town of Pravetz includes rehabilitation of basketball and volleyball playground. .101 on the plan of Pravetz
Overview
| Status | Contracted |
|---|---|
| Start date | 08 May, 2019 |
| End date | 08 May, 2022 |
| Contract date | 08 May, 2019 |
Programme
Beneficiary
Financial information
| Total cost | 92,489.00 |
|---|---|
| Grant | 92,489.00 |
| Self finance | 0.00 |
| Total paid | 41,749.50 |
| EU participation percent | 85.0% |
Location