The dismantling of an asphalt pavement of 29x16m is planned for the construction of a sports ground for 3 types of sports - football, basketball and handball. The activity covers the removal and removal of the asphalt pavement. Sealing a ground bed for crushed stone. After the laying of the crushed stone facade, a reinforced concrete screed is planned. The surface will be flattened by grinding. The new course will be 28x15. The flooring will be made of rubber material designed for 3 types of sports. The newly built playground will be protected by a grid that is fastened to galvanized stakes. We provide delivery and installation of basketball bins and soccer gates.
Overview
Status | Contracted |
---|---|
Start date | 10 May, 2019 |
End date | 10 May, 2022 |
Contract date | 10 May, 2019 |
Programme
Beneficiary
Financial information
Total cost | 97,681.84 |
---|---|
Grant | 97,681.84 |
Self finance | 0.00 |
Total paid | 0.00 |
EU participation percent | 85.0% |