The project proposal envisages the reconstruction and rehabilitation of forest roads with a total length of 8348,30 in the forest territory of Elin Pelin, as well as the construction of a new tank for fire-fighting purposes, construction of mineralized strips and firebreaks.
Overview
| Status | Contracted |
|---|---|
| Start date | 29 Sep, 2020 |
| End date | 15 Sep, 2023 |
| Contract date | 29 Sep, 2020 |
Programme
Beneficiary
Financial information
| Total cost | 2,018,466.62 |
|---|---|
| Grant | 2,018,466.62 |
| Self finance | 0.00 |
| Total paid | 0.00 |
| EU participation percent | 85.0% |