Rehabilitation of Railway line Plovdiv – Burgas, Phase 2

With the implementation of the project is envisaged to rehabilitate and modernize the rest not yet renewed railway sections along the railway line Plovdiv–Burgas, namely: • Component 1–Design and installation of system for signalling and telecommunication along the railway line Plovdiv–Burgas–signaling in 18 stations; installation of: train control system ETCS, level 1; system for centralized train dispatcher`s office in the section Manole–Burgas; train communication system GSM-R and optic cable; • Component 2-Construction of overpasses/underpasses along the railway line Plovdiv-Burgas to replace existing level crossing; • Component 3-Estabilishment of protective forest belt in section Chernograd-Aytos to protect track from adverse weather conditions; • Component 4-Rehabilitation of the railway section Skutare-Orizovo-renewal of railway track, reconstruction of bridges and existing catenary, renewal of the signalling in stations; • Component 5- Modernisation of railway section Orizovo-Mihaylovo-renewal and construction of railway track and catenary, reconstruction of bridges, construction of a tunnel, modernization of track sub-station Chirpan, removal of level crossing and construction of overpasses and renewal of signallin in stations; • Component 6-Modernisation of railway section Yambol-Zimnitsa at Zavoy station-newly constructed railway track incl. in Zavoy station, newly constructed bridges, renewal of existing and newly constructed catenary; • Component 7-Reconstruction of switches layot in Zimnitsa station and rehabilitation of catenary in the station Zimnitsa and Straldzha-renewal of railway track, reconstructed permanent layout in Zimnitsa station, renewal of existing catenary in Zimnitsa and Straldzha stations and renewal of signaling in Zimnitsa station; • Component 8-Rehabilitation or railway section Straldzha-Tserkovsi-renewal of railway track. Detailed information is presented in B.3.1 in the AF and Annex 1.

Comments
Leave a comment

Overview

Status In execution (starting date)
Start date 01 Feb, 2016
End date 31 Dec, 2022
Contract date 20 Nov, 2017
View in UMIS

Financial information

Total cost 810,018,562.65
Grant 563,158,135.86
Self finance 246,860,426.79
Total paid 197,517,435.99
EU participation percent 85.0%

Location

South Central (BG42)