With the implementation of the project is envisaged to rehabilitate and modernize the rest not yet renewed railway sections along the railway line Plovdiv–Burgas, namely: • Component 1–Design and installation of system for signalling and telecommunication along the railway line Plovdiv–Burgas–signaling in 18 stations; installation of: train control system ETCS, level 1; system for centralized train dispatcher`s office in the section Manole–Burgas; train communication system GSM-R and optic cable; • Component 2-Construction of overpasses/underpasses along the railway line Plovdiv-Burgas to replace existing level crossing; • Component 3-Estabilishment of protective forest belt in section Chernograd-Aytos to protect track from adverse weather conditions; • Component 4-Rehabilitation of the railway section Skutare-Orizovo-renewal of railway track, reconstruction of bridges and existing catenary, renewal of the signalling in stations; • Component 5- Modernisation of railway section Orizovo-Mihaylovo-renewal and construction of railway track and catenary, reconstruction of bridges, construction of a tunnel, modernization of track sub-station Chirpan, removal of level crossing and construction of overpasses and renewal of signallin in stations; • Component 6-Modernisation of railway section Yambol-Zimnitsa at Zavoy station-newly constructed railway track incl. in Zavoy station, newly constructed bridges, renewal of existing and newly constructed catenary; • Component 7-Reconstruction of switches layot in Zimnitsa station and rehabilitation of catenary in the station Zimnitsa and Straldzha-renewal of railway track, reconstructed permanent layout in Zimnitsa station, renewal of existing catenary in Zimnitsa and Straldzha stations and renewal of signaling in Zimnitsa station; • Component 8-Rehabilitation or railway section Straldzha-Tserkovsi-renewal of railway track. Detailed information is presented in B.3.1 in the AF and Annex 1.
Overview
Status | In execution (starting date) |
---|---|
Start date | 01 Feb, 2016 |
End date | 31 Dec, 2022 |
Contract date | 20 Nov, 2017 |
Programme
Beneficiary
Financial information
Total cost | 810,018,562.65 |
---|---|
Grant | 563,158,135.86 |
Self finance | 246,860,426.79 |
Total paid | 197,517,435.99 |
EU participation percent | 85.0% |
Location