Increasing energy and resource efficiency of IKI Ltd.

The company "IKI" Ltd. was founded in 2005 with headquarters. Stara Zagora with activities related to the provision of services in the road construction sector. Has a production base rent for storage and repair of machines, the area of ​​which is about 350 m2. Currently the company has two Backhoe used for housing and road construction, construction of water and sewage networks, earth works, handling and disposal of inert materials and laying of pavements and others. Currently the machines are working for the construction and repair of streets and spaces. The company participated in the construction of Lot 1 and Lot 2 of Trakia highway. Through the project proposal will purchase a number of wheel excavators and hammer (Measure 1), a number backhoe loader (Measure 2) a number of ventilation system in the production facility for recovery of residual heat (Measure 3) monitoring systems energy Measure 1 - Wheeled Excavator Hammer (Measure 4), which will reduce the consumption of diesel and energy, and improving the efficiency of the company.

Comments
Leave a comment

Overview

Status Closed (completion date)
Start date 09 Aug, 2017
End date 14 Sep, 2018
Contract date 09 Aug, 2017
View in UMIS

Beneficiary

Financial information

Total cost 493,791.99
Grant 353,234.39
Self finance 140,557.60
Total paid 352,672.71
EU participation percent 85.0%

Location