The project proposal envisages the implementation of energy saving measures, prescribed in the prepared energy efficiency report of Street Lighting at Marin Boev Street, Georgi Dimitrov Street, 23 Septemvri Street, Otets Paisiy Street, Cyril and Methodius "," Raina Knyaginya "," Hristo Botev ","Dimitar Blagoev "," Hristo Smirnenski "," Georgi Mihailov "," Rayko Daskalov "," St. Ivan Vazov "and Philip Totyu Street in Knezha, Knezha Municipality. According to the regulation, the following measures are envisaged: 1. Replacement of luminaires with new LED luminaires: The proposed measure includes replacement of all luminaires with new Led luminaires with power from 22 to 100W, min. 120-140lm / W. The luminaires must have zero light upward. The luminaires will have electronic ballast and a efficiency of 95%. 2. Installation of solar lamps for sidewalk lighting: The possibility of using renewable energy sources to supply street lighting on sidewalks has been evaluated. It is possible to use a solar lamp with a built-in battery with a power of 20W, without the need for additional power supply. The measure will save 12% of total energy consumption after ECM. 150pcs will be installed. solar lamps placed on the existing pillars along the streets: Marin Boev, Georgi Dimitrov and Rayko Daskalov. 3. Introduction of a street lighting control system, resulting in a reduction of the lighting power in hours with reduced movement between 0 and 5 hours. When the street lamp is switched on, it will start operating at 100% of its power, at 00:00 it will decrease to 50% and at 05:00 it will be switched on again at 100%. This will lead to normal lighting with significant energy savings The envisaged project is 683 990.35 BGN for a period of 18 months. The activities are implemented in cooperation with the Norwegian partner Executive Decision Support AS.
Здравейте кога ще се сменят лампите с новите лед при ул Райко Даскалов град.кнежа кажете
16 Jan, 2022
Overview
Status | In execution (starting date) |
---|---|
Start date | 09 Mar, 2021 |
End date | 09 Sep, 2022 |
Contract date | 09 Mar, 2021 |
Beneficiary
Financial information
Total cost | 683,990.35 |
---|---|
Grant | 683,990.35 |
Self finance | 0.00 |
Total paid | 205,197.00 |
EU participation percent | 85.0% |
Location