26 project

Implementing energy efficiency measures in public infrastructure, building of District Court Ivaylovgrad, Ivaylovgrad

Total cost

146,552.92

Grant

144,552.92

Self finance

2,000.00

Total paid

134,890.31

Status

Closed (completion date)

Contract date

09 Sep, 2016

Start date

09 Sep, 2016

End date

08 Aug, 2019

Together we are better

Total cost

487,841.81

Grant

487,841.81

Self finance

0.00

Total paid

324,130.92

Status

Closed (completion date)

Contract date

02 Aug, 2016

Start date

02 Aug, 2016

End date

06 Jun, 2019

Implementing energy efficiency measures of public infrastructure , building of the Regional Service "Fire Safety and Population Protection " - Ivaylovgrad .

Total cost

213,076.16

Grant

213,076.16

Self finance

0.00

Total paid

197,848.89

Status

Closed (completion date)

Contract date

09 Sep, 2016

Start date

09 Sep, 2016

End date

03 May, 2019

"Providing a hot lunch in the municipality of Ivaylovgrad"

Total cost

14,501.85

Grant

14,501.85

Self finance

0.00

Total paid

14,501.95

Status

Closed (completion date)

Contract date

21 Sep, 2016

Start date

01 Aug, 2016

End date

31 Dec, 2017

Social Support At Home

Total cost

499,639.20

Grant

499,639.20

Self finance

0.00

Total paid

494,169.82

Status

Closed (completion date)

Contract date

09 Dec, 2015

Start date

09 Dec, 2015

End date

09 Oct, 2017

Providing a warm meal in the municipality of IVAYLOVGRAD

Total cost

5,861.80

Grant

5,861.80

Self finance

0.00

Total paid

5,861.78

Status

Closed (completion date)

Contract date

05 Jun, 2015

Start date

04 May, 2015

End date

30 Sep, 2015